Land Development

Land Development of Astoria Community

Market Sector: Residential Land Development

Full SWPPP Installation, Maintenance & Removal of all BMPs 


Erosion & Construction Services provided comprehensive SWPPP installation and ongoing maintenance for the Lennar Astoria land development, supporting site compliance across multiple phases of grading, infrastructure installation, and residential construction. ECS worked as a long-term erosion control partner, responding to evolving site conditions, weather impacts, and municipal inspection requirements to protect adjacent properties and downstream waterways.

As the project progressed, ECS adjusted and maintained erosion and sediment control measures to align with active construction sequencing and ultimately completed BMP removal as areas reached final stabilization.

 

Services Completed:

  • Site Preparation
    • SWPPP Sign Installation
    • Concrete Washout Installation and Maintenance
  • Perimeter Control Installation & Maintenance
    • Silt fence 
    • Siltworm™ filter sock 
    • Hi-visibility safety fence 
    • Snow fence
  • Inlet Protection
    • Storm drain and curb inlet baskets
    • Yard inlet baskets
    • Above-ground inlet protection 
  • Street Sediment Management
    • Street sweeping
    • Curb scraping and sediment removal 
  • Phase Closeout
    • Removal of temporary sediment and erosion control BMPs as areas achieved final stabilization

Project Details
Location: Northwest Indiana
Engagement Duration: Multi-phase, ongoing 12+ Months
Project Partner: Lennar

Why This Project Matters

Large-scale residential developments require erosion control partners who can remain engaged over time and adapt as site conditions evolve. At Astoria, ECS provided consistent SWPPP installation, maintenance, and closeout services that supported compliance while allowing construction activities to continue without interruption.


Need help with your Land Development Project?